Pak-India Water Disputes
The POST,
Sun, Feb,26, 2006.
Pervaiz Iqbal Cheema
Among the serious disputes that were the product of
hasty, unimaginative and surgical partition of the British India, the water
dispute and the ongoing Kashmir dispute were probably most complicated. The
water dispute surfaced when the Indian Punjab cut off the flow of waters in
April 1948. Given the uncertainty of rains, agriculture was heavily dependent
upon the river waters. No dispute generated so much bitterness as did the one
over the flow of waters to Pakistan. Neither Kashmir nor any other dispute
could induce Pakistan to begin to entertain the possibility of a full fledged
war with India except the water dispute.
India and Pakistan attempted to resolve the dispute but were
unable to find a permanent solution, though interim arrangements provided a
temporary respite for Pakistani farmers. Eventually through the efforts of
World Bank President Mr. Eugene Black the dispute was resolved and Indus Water
Treaty was signed between the two countries. The treaty allotted the waters of
three western rivers (Indus, Jhelum, Chenab) and those of eastern rivers (Ravi,
Bias, Sutlej) to India. The treaty also envisaged the construction of link
canal system, storage dams, power generation and an elaborate network of tube
wells for drainage purposes. For smooth operation of the treaty a permanent
India-Pakistan Indus Commission was established.
By and large the Indus Water Treaty has been working
smoothly and minor irritations were effectively handled by the Commission to
the satisfaction of both countries. However in recent times not only the
treaty has been subjected to serious criticism but the violation of its many
provisions has raised new issues. Voices particularly from the Indian Held
Kashmir went suggested to scrap the treaty and to renegotiate the distribution
of waters. Simultaneously three disputes related to the provisions of the
treaty have surfaced. These dispute are Wullar Lake Barrage, Baghilhar Dam and
Kishanganga Project.
The Wullar Lake barrage issue emerged in 1985 when Pakistan
came to know about Indian plans to construct a barrage on the Wullar Lake
which was known in India as Tulbul navigation project. The barrage was to be
constructed on river Jhelum near the town of Sopor where it flows out of the
lake. The Indian stated objected was to construct the barrage for the improved
navigational facilities in the river Jhelum during the winter season. For
Pakistan the main worry was a barrage on that site could jeopardize and
effectively damage the three canal system consisting of Upper Jhelum Canal,
Upper Chenab Canal and Lower Bari Doab Canal.
India argued that Tulbul project would be beneficial for the
Pakistanis as it would regulate the supply of waters to Mangla Dam which would
increase Pakistan’s capacity to generate electricity as well as to regulate
the irrigation through the above mentioned Canal system. Pakistan argued that
India has violated the Indus Water Treaty. The Pakistani quoted the relevant
provision of the treaty which clearly stipulated that India is entitled to
construct an ‘incidental storage capacity’ provided the design has been
examined and approved by Pakistan on one hand and the storage capacity of does
not exceed 0.1 MAF of water on the other. It needs to be mentioned here that
the capacity of Wullar Lake barrage is 3.0MAF.
As per provisions of the treaty the case was referred to the
Permanent Indus Commission in 1986 but it could not resolve it and by 1987 it
recorded its failure. The Indian stopped the construction work on the project,
the Pakistanis decided not to refer it to the World Bank. The ensuing period
witnessed several rounds of talks between the two parties but they could not
reach an agreement. In 2005 the Indians changed the structural design but it
was once again rejected by the Pakistanis on grounds that it was against the
spirit and provision of the Indus water Treaty. Pakistan feels that it could
not allow India to have a 30 times more storage capacity than what is
permitted by the treaty.
The second dispute is over the Baglihar Dam; a 450 MW
(eventually 900 MW) hydropower project is being constructed on the river
Chenab. This project has serious repercussion for Pakistan. The Pakistanis
argue that India stores waters in a reservoir behind the gated spillways
depriving Pakistan its share of Chenab waters which is a violation of the
Indus water treaty. The construction on the Baglihar dam project on the river
Chenab started in 1999 though it was conceived and approved much earlier. In
order to quickly complete the project the Indians have currently employed
several hundreds of engineers and the laborers. The reports indicated that
they have hired the services of many more individuals to speed up the
construction work with ostensible aim of confronting Pakistan with a fait
accompli.
The Pakistanis had conveyed their objections and reservation
regarding the design of the project despite the fact that the requested
requisite data was never supplied quickly. According to the Indus water treaty
of 1960, the unrestricted flow of Chenab waters was allocated to Pakistan.
However it needs to be mentioned here that India was allowed the use of
limited waters of western rivers for development of irrigation, generation of
electric power along with other uses that were spelled out in the annexes of
the treaty.
Pakistan’s objection and reservations about the project
primarily deals with the design which allows more flow of waters than what is
permissible under the Indus water treaty. On learning about the construction
the Pakistanis raised their objections which India, tried to ignore initially
but later began to respond somewhat hesitantly. Even the Pakistanis were
allowed to visit the site. After the visit the Pakistanis became even more
convinced that if the dam is constructed in accordance with the current
design, Pakistan is likely to lose 7000 to 8000 cusecs a day. This implies
that Pakistan will have to learn to live with these losses.
Cognizant of the likely losses the Pakistanis initially
tried to have the necessary rectification of design done at the Indus
Commissioners level but once they were unable to secure a desired agreement,
the dispute-level was raised to the level of secretaries of water and power.
The two sides have met many times but have so far not been able to work out a
mutually acceptable agreement. Eventually the dispute was referred to the
World Bank and a neutral expert was appointed who, after listening to both
sides is in the process of finalizing his verdict.
Judged by any yardstick the failure to reach an agreement
over the Baglihar dam is bound to take not only a heavy chunk of existing
goodwill and cordiality of atmosphere but would also strengthen the belief
that India is employing age old delaying tactics. Whether or not this failure
would adversely impact upon the ongoing composite dialogue remains to be seen
but there is no doubt it would certainly dampen the existing optimism.
The third emerging dispute is over the Indian announced
intention to construct 330 MW Kishangange hydro project. For this project
India intends to divert the waters of the Neelam River. When Kishangane River
enters Pakistani Kashmir it is known as Neelam River. River Neelam is an
important tributary of river Jhelum. Pakistan has articulated its objections
in the form of six questions; three are related to the design, two on
diversion and one on power house. The diversion tunnel would reduce the flow
of water by 27%. Besides Pakistan has a plan to construct 969 MW hydropower
project on the river Neelam. In fact they have already spent 71 million rupees
on it. Similarly the Indians have completed 75% tunnel construction work.
Since Indians have demonstrated a tendency to work fast and present the
Pakistanis a fait accompli, they have already accelerated the work. Pakistan
has decided in Nov. 2005 to refer the case to World Bank soon.
The writer works for Islamabad Policy Research Institute.
|